Bridge St / Lion Ln Reconstruction

Print
Press Enter to show all options, press Tab go to next option

CONTACT INFORMATION 

651.490.4650

David Yang, Staff Engineer

Phone: 651.490.4664 | E-mail David

Shoreview’s 2018 Capital Improvement Program includes the reconstruction of the roads in the Bridge Lion Road Reconstruction.

Construction Newsletter #2

Update 7-6-18

Due to rain delay the start of the project has been pushed back a week. Pavement reclamation is scheduled for the week of July 23rd with the installation of the underground utilities to follow. 

Update 6-29-18

The gas contractor will continue to finish up installing gas mains and services. No road work is expected in that area.

Update 6-22-18

Pavement removal will take place July 9th - July 16th. Installation of underground piping will begin July 16th and last approximately 3 weeks. Q-3 will continue to install new gas main and services and the tree contractor may be back next week to continue work on tree removal. Please continue removing plants and landscaping material from the right-of-way. Additionally, please move any irrigation lines in the right-of-way back 5 or 6 feet so they are not damaged.

Update 6-12-18

Tree removal is expected to be completed the week of June 24th, the existing asphalt surface is expected to be removed the week of July 2nd, and the installation of underground piping is planned to start the week of July 9th.

Update 05-11-18

Bids were received and the award will be presented at the May 21st City Council meeting.

Update 05-02-18

Preliminary Exhibit for Bridge St

Preliminary Exhibit for Lion Ln

Public Hearing for Bridge St and Lion Ln

Bridge / Lion Update 11-14-17

Click on the following links to view PowerPoint presentations

Resident Meeting 11-09-17

Project Map

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer