Bridge St / Lion Ln Reconstruction

Print
Press Enter to show all options, press Tab go to next option

 


CONTACT INFORMATION 

651.490.4650

David Yang, Staff Engineer

Phone: 651.490.4664 | E-mail David

Shoreview’s 2018 Capital Improvement Program includes the reconstruction of the roads in the Bridge Lion Road Reconstruction.

Update 10-12-18

The first layer of pavement is scheduled for Monday, October 12th depending how much progress the contractor makes in grading and prepping the road base. You will be able to drive on the asphalt as soon as the rollers have made their passes. Please note that you may be momentarily delayed for up to an hour if the contractor is paving in front of your driveway or at the intersections. We ask that you continue to use caution while driving through the construction site and next to heavy equipment

Update 10-5-18

The contractor is working to complete the installation of concrete curb and gutter on Bridge Street and Lion Lane, and is scheduled to pour concrete driveways on Saturday, October 6th, weather permitting. Please avoid driving on the new concrete curb and driveways for the next 7 days after it has been installed to allow it to gain the strength to support the weight of a vehicle. You may park your car in front of your home during 7 PM to 7 AM. Work to prep the road base for the first layer of pavement will follow the installation of the concrete curb and gutter. Thank you for your continued cooperation and patience, it is greatly appreciated.

Update 9-28-18

Prepping of the road base for curb and pavement will be completed by next Monday. On Tuesday, October 2nd, please have any vehicles, boats, and trailers that you will need for the following seven days out of your driveway by 7:00 AM. The contractor is scheduled to start working on installing the new concrete curb and driveways if the weather permits. Once the new concrete has been installed, please do not drive on it for seven days. During this time, please park your vehicles on Bridge Street or Lion Lane east of Galtier Street. You may park your car on the road in front of your house between 7:00 PM and 7:00 AM during nonworking hours.
Although it can be tempting to drive on the new concrete, it needs time to fully harden to support the weight of a vehicle to prevent it from getting damaged. Please also avoid walking or riding a bike on the new concrete for at least 24 hours after it has been installed. Your cooperation is appreciated

 

Update 9-21-18

All the major underground work will be complete with only miscellaneous work remaining. The contractor will begin preparation of the road to get it to the correct elevation and start spreading the gravel for the installation of the curb and gutter, therefore, residents should have their vehicles needed out of driveways by 7:00 am and parked on adjacent streets to the project.

Update 9-14-18

The contractor will continue to install the storm sewer and finish up with a few sanitary sewer services. The contractor will start installing the new fire hydrants and gate valves in which water to residents will be turned off on Tuesday to start the replacement work. Grading crew will also be grading the road and prepping for gravel and curb and gutter.

Bridge / Lion Construction Newsletter #3

Update 9-6-18

The contractor will continue making  repairs to the sanitary sewer services and installing the new storm sewer collection and infiltration system into the week of September 10.

Update 8-31-18

The contractor is currently working on sanitary services and installing the storm sewer collection and infiltration system.

Update 8-24-18

The contractor will continue to work on sanitary sewer services and also will start storm sewer installation sometime during the week. Residents in that area should also have any vehicle needed moved out of their driveways by 7:00 am and parked on adjacent streets to the project area. 

Update 8-17-18

The contractor has begun work on replacing sanitary sewer and installing cleanouts on Lion Lane, and will continue with that into the week of August 20th. The contractor responsible for tree removals will be back the week of August 20th to grind down the tree stumps.Please continue to be cautious when driving through the construction zone for your own safety and for those around you. We also ask that all parents talk with your children about the dangers of the construction site.

Update 8-3-18

Due to weather and other unforeseen circumstances, the contractor is a week or two behind schedule as they continue working in Dale Court North, Dale Court South, Dale Street North, and Arner Avenue. This has pushed the schedule up for work in Bridge Street and Lion Lane. The current schedule has tree removals planned for the week of August 6th on Bridge Street and Lion Lane, and removal of the existing pavement on August 13th assuming no major delays are encountered before then. Once removals are completed, the contractor will begin installing the underground utilities, including sanitary sewer clean-outs and the stormwater collection and infiltration system.

Construction Newsletter #2

Update 7-6-18

Due to rain delay the start of the project has been pushed back a week. Pavement reclamation is scheduled for the week of July 23rd with the installation of the underground utilities to follow. 

Update 6-29-18

The gas contractor will continue to finish up installing gas mains and services. No road work is expected in that area.

 

Update 6-22-18

Pavement removal will take place July 9th - July 16th. Installation of underground piping will begin July 16th and last approximately 3 weeks. Q-3 will continue to install new gas main and services and the tree contractor may be back next week to continue work on tree removal. Please continue removing plants and landscaping material from the right-of-way. Additionally, please move any irrigation lines in the right-of-way back 5 or 6 feet so they are not damaged.

 

Update 6-12-18

Tree removal is expected to be completed the week of June 24th, the existing asphalt surface is expected to be removed the week of July 2nd, and the installation of underground piping is planned to start the week of July 9th.

Update 05-11-18

Bids were received and the award will be presented at the May 21st City Council meeting.

Update 05-02-18

Preliminary Exhibit for Bridge St

Preliminary Exhibit for Lion Ln

Public Hearing for Bridge St and Lion Ln

Bridge / Lion Update 11-14-17

Click on the following links to view PowerPoint presentations

Resident Meeting 11-09-17

Project Map

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer