Edgetown Acres Reconstruction - Phase 1

Project Map

Update October 16, 2019

The first resident information meeting was held on October 15, 2019. Information provided at the meeting included existing conditions of streets and City utilities, improvement goals, impacts to residents during construction, typical construction, communication, special assessments, and proposed schedule. 

Resident Meeting Presentation

Overview

The City is proposing to reconstruct the Edgetown Acres Neighborhood. Due to the size of the neighborhood, the project will be completed over two years, 2020 (phase 1) & 2021 (phase 2) as shown on the map.
Streets proposed for Phase 1 - 2020 include:
  • Pinewood, Terrace, and Oakwood Drives from Fairview Avenue to Aldine Street
  • Fairview Avenue from County Road I to the cul-de-sac
Streets proposed for Phase 2 - 2021 include:
  • Hillview Road and Lois Drive from Fairview Avenue to Snelling Avenue
  • Aldine Street from County Road I to Lois Drive
Proposed improvements for Phase 1 include:
  • Replacing the road surface & installing concrete curb & gutter
  • Repairs/replacement of sanitary sewer & water systems
  • Installing a stormwater collection & treatment system
  • Addition of street lights
The first neighborhood meeting for the Phase 1 area is scheduled for:
Tuesday, October 15, starting at 6:30 pm
Shoreview City Hall Council Chambers

 

Contact Information

Tom Wesolowski - City Engineer

 651-490-4652 E-mail Tom