Gramsie Road Rehabilitation

Print
Press Enter to show all options, press Tab go to next option
CONTACT INFORMATION 

651.490.4650

David Yang,

Staff Engineer

Phone: 651.490.4664 |E-mail David

 

Shoreview's 2016 Capital Improvement Program includes the rehabilitation of the pavement on Gramsie Road from Victoria Street east to Gramsie Court.

The project was awarded to Northwest Asphalt. The City is currently working with the contractor on a construction schedule for the project. 

Gramsie Road Rehabilitation Map

Check this section for weekly construction updates.

Gramsie Road Update 11-21-17

The roadwork is complete and now open.

Gramsie Road Update 11-13-17

The base layer of asphalt has been paved and the road has been striped for traffic. Before the road is open to traffic, the guardrails on the north and south side of the road and the fence along the trail have to be installed. This work, along with site restoration, is scheduled to be completed by the end of the week.

Gramsie Road Update 10-30-17

The contractor is finishing grading the road and plans to pave the first lift of asphalt on Tuesday, October 31st. Gramsie Road is still closed to traffic, please continue to use alternative routes. Thank you for your continued cooperation and patience.

Gramsie Road Update 10-20-17

The retaining wall on the south side of Gramsie Road has been completed. The contractor will begin grading the road for paving. Gramsie Road is still closed to traffic.

Gramsie Road Update 10-13-17

Gramsie Road is now closed to traffic for the next 4 to 6 weeks. Residents on Gramsie Road will have access to their driveways throughout the project. The contractor has reclaimed the pavement and underlying base material on the existing road and trail and is now in the process of building a new retaining wall on the south side of the road. Work on the retaining wall will take a few days and be completed by early next week.

Gramsie Road Update 10-04-17

Gramsie Road will be closed starting Monday, October 9th between Mackubin Street and Hodgson Road for road construction. The temporary section of Gramsie Road will be permanently raised above current flood levels. This work is expected to take from 4 to 6 weeks depending on the weather. Please plan to use alternative routes. Thank you for your cooperation.

Gramsie Road Update 11-04-16

Temporary repairs to Gramsie Road have been completed, and it is now open to traffic. Due to the temporary nature of the repairs, we ask traffic to slow down. The speed limit has been reduced to 25 mph through the raised area.

The contractor will be working on the bike path along Gramsie starting Monday, August 15th and should be paved by the end of the day of August 16th, the sodding contractor is scheduled forWednesday, August 17th. Weather and schedule permitting, the final lift of pavement could be placed as early as the week of August 22nd.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer