Shutta Road Sanitary Sewer Improvements

Print
Press Enter to show all options, press Tab go to next option

Contact Information

Tom Wesolowski, City Engineer

651-490-4652 | E-mail Tom

Proposed improvements include the relocation of a sanitary sewer line north of Schutta Road in the Rice Creek Regional Park to address operational issues.

Schutta Road Project Location Map

Update 12-6-2019

The contractor has completed the installation of the new sanitary sewer pipe and connected the new pipe to the existing sanitary sewer located at the intersection of Schutta Road and Lois Drive.  The paved areas that were removed on Schutta Road will be restored with a gravel surface, which will be maintained by the City over the winter.  Pavement will be installed in the spring along with any concrete curb and gutter sections that were removed. The week of December 9, the contractor will remove the dewatering equipment, abandon the old sanitary sewer infrastructure, and restore the disturbed areas. The contractor will then stop work for the season.

Update 11-22-2019

This week the contractor installed sanitary sewer pipe to the south around the wetland along with two manholes.
The week of November 25 the contractor will continue to install sanitary sewer pipe and associated manholes to the south around the wetland area.

Update 11-15-2019

During the week of November 11, the contractor installed the de-watering systems, installed the manhole over the existing pipe at the north end connection point, and began the installation of pipe from the manhole to the south.  
The week of November 18, the contractor plans to continue the installation of the pipe to the south and install manhole structures as required.

Update 11-8-2019

The contractor moved on site this week to remove trees and shrubs and installed erosion control. Next week they will start the installation of the underground piping.

Update 9-13-2019

The City and County are in the process of finalizing the agreement to allow the installation of the sanitary sewer pipe. It is expected the work will start in mid to late October.

Update 6-17-2019

The City is currently working with Ramsey County on an easement agreement to allow the installation of the sanitary sewer piping. Once the agreement is completed the installation of the sewer pipe will begin.

Update 4-19-19

Project was awarded to Pember Companies at the April 1 Council meeting. Construction on the project is expected to start in late May/early June.